Gongyi Xiaoyi Jinwang Machinery Factory

Gongyi Xiaoyi Jinwang Machinery Factory

One corner of brick making factory

2022 03/26

1. The equipment should be installed on a horizontal concrete foundation and fixed with anchor bolts.
2. When installing, pay attention to the verticality of the main body and the level.
3. After installation, check whether the bolts of various parts are loose and whether the main engine compartment door is tightened. If so, please tighten it.
4. Configure the power cord and control switch according to the power of the equipment.

5. After the inspection is completed, carry out an empty-load test run, and the test run is normal and the production can be carried out.